The non-qualification review assessment window is now open. By 15 June 2023 National Grid (NG) ESO will assess any non-qualifying applications that were submitted for review.

NG ESO informed all Allocation Round 5 (AR5) applicants of the outcome of their application following the qualification assessment window, which concluded on 24 May 2023. 
 
Between 25 May to 1 June 2023, any applicants that did not qualify could submit a request for NG ESO to review its decision.  
 
NG ESO will review the relevant applications by 15 June 2023. 
 
For further information, view the original AR5 timeline scenarios. Following NG ESO receiving non-qualifying applications, scenarios 1 and 2 are no longer applicable for AR5.